Emailing SiteManager Custom Reports

The option to send SiteManager custom reports directly to your email has returned.

Thank you,

Monday, October 1, 2012

Temporary Instructions for emailing PDF reports from SM Report Server

The attached document illustrates one method of emailing PDF reports from the custom report server. It may be helpful to you and others while the customary email option is temporarily unavailable.

 

Thank you,

 

 

 

 

IMPORTANT: SiteManager Report Server

IMPORTANT: SiteManager Report Server

 

The option to email reports has temporarily been removed. It will return as an option when ISD has resolved an existing issue.

 

For now the all reports will be generated with the default option to view in web.

 

We apologies for the inconvenience. 

 

 

Wednesday, August 29, 2012

SiteManager Change Order Franchise Process

Please review:
 
It is CST intention in the next month or so to update SiteManager to include a modification to allow for the change order franchise rules.
 
The change will mimic the change order override option (those not familiar with this option see attached).
 
SiteManager will not be charged with the task of determining appropriate approval levels. Approval groups will not be automatically determined or calculated by dollar amount, function or other process. 
 
Under the franchise model, District discretion will be used to manually select approval levels. Approval groups will be assigned in a process that is identical to the override option.

 

Minimum requirements :

1.    A minimum of one Area Engineer or District Engineer must be included with each change order approval.

2.    A minumum of two different users must approve each change order.


More specific information as to the date and time for the update will be sent as it becomes known.
 
Thank you,
 
Stewart
===================  Hurricane Season:  Hurricane season is underway.   Do you have a Personal Plan for your family�s safety?  Visit www.txdot.gov/travel/hurricane.htm

SiteManager offline Sunday Sept 9th 10-12pm

Greeting,
SiteManager, EPRS and all dependant reporting services will be offline for routine maintenance on the morning of Sunday, September the 9th between the hours of 10-12pm. Please forward this information to all parties that may be affected by this outage.
 
Thank you,  

 
 
 
Stewart DeWitt
CST-Construction Division
Senior SiteManager Succor™
Phone: (512) 416-2462
stewart.dewitt@txdot.gov
>>> On 8/29/2012 at 11:10 AM, in message <93A8FAE9FA985A44905D349E74C0C410CE69A2@BLUPRD0611MB401.namprd06.prod.outlook.com>, Jay Edwards <Jay.Edwards@txdot.gov> wrote:

Date:                     Sunday September 9th

Start Time:          10:00 AM

Duration:             2 hrs

 

TX-SM-PD and TX-SM-PD2 have been up nearly 700 days without a restart. This reboot is to primarily clear out paging but also to reset everything. Normally we would have had to reboot the servers due to maintenance of some sort by this time.

 

Streams replication will be shutdown prior the reboot then restarted afterwards.

The SMGRPS replication will be delayed till after the reboot is complete.

 

Oracle instances: SMGRPRD, SMGRADHC, TXDB9 and SMGRPS

 

Production databases that will be offline during during the reboot: SiteManager, SiteManager Adhoc, EPRS, LIMS, Central Permit System, SiteManager Production Support, DSS, E1391

 

Please let me know if someone is to be contacted and if so how (email, phone etc…) after the reboot is complete.

 

If there are questions or comments please let us know.

===================  Hurricane Season:  Hurricane season is underway.   Do you have a Personal Plan for your family�s safety?  Visit www.txdot.gov/travel/hurricane.htm

Friday, August 17, 2012

New SiteManager Website

Greetings,
We have updated the SiteManager website. Please update your bookmarks to http://crossroads/org/cst/cmisd/sitemgr.asp
 
You'll want to check out the dedicated report pages. Each page has a table or grid with filterable fields to allow you to narrow your search and hone in on the right report. Finding the information you're searching for will never be easier.
 
The Statewide Construction Report developed by Mike Lehmann that previously was on the San Antonio website is now available here (http://crossroads/org/cst/cmisd/sitemgr.asp?m=smgr&p=swcreport).
 
The "How to Videos" are still evolving so I ask for your patience as more are created.
 
Enjoy, 
 
 
 
 
 
Stewart DeWitt
CST-Construction Division
Senior SiteManager Succor™
Phone: (512) 416-2462
stewart.dewitt@txdot.gov
===================  Hurricane Season:  Hurricane season is underway.   Do you have a Personal Plan for your family�s safety?  Visit www.txdot.gov/travel/hurricane.htm

Monday, July 16, 2012

Material Usage available on the XiteReport

The Material Usage sheet is a recent addition to the XiteReport. The additional sheet displays the total used quantity of materials given a user defined set of parameters. Glenn Eilert prepared the attached Word document that demonstrates how it can be used to determine the quantity of coarse aggregate material used for a given set of bid items by manipulating the report's column filters.

Material quantities are determined by calculating the paid, installed, or reported item quantities by the item's material conversion factor. Please note that the calculated material quantity is only as accurate as the material's conversion factor and it is provided "as is" without warranty of any kind , either expressed or implied.




Enjoy,


 
 
 
 
Stewart DeWitt
CST-Construction Division
Senior SiteManager Succor™
Phone: (512) 416-2462
stewart.dewitt@txdot.gov
===================  Hurricane Season:  Hurricane season is underway.   Do you have a Personal Plan for your family�s safety?  Visit www.txdot.gov/travel/hurricane.htm